Galvanised Pole And New Switchboard – Turramurra

Aug 9, 2022

TURRAMURRA, NSW

Service: Galvanised Pole And New Switchboard


Problem:
After a 2 year build this home in Turramurra was ready to be connected to the grid with a permanent 3 phase 100 Amp supply.

Solution:
A 7.2m Galvanised pole was required to gain appropriate clearance over Bobbin Head Road. 25MM underground consumer mains were installed and terminated ready for use by the energy retailer at the new main switchboard.The temporary builders supply we installed when the build started was removed and the new supply energized and tested.