Defect Rectification of Non Compliant Point of Attachment – Wheeler Heights

Wheeler Heights, NSW

Service: Defect Rectification of Non Compliant Point of Attachment (POA)


Problem:
Our clients were issued with a defect notification in regards to a non-compliant electrical supply point of attachment.

Solution:
A recent deck renovation meant the point of attachment was functional but unfortunately not up to regulation.
We manufactured a timber frame which was anchored to the existing deck.
The existing consumer mains were extended and installed in conduit up to the new point of attachment.
The defect has now been cleared and the new point of attachment now offers a safe isolation point in case of an emergency.